There is a tutorial on how to create a burndown chart for Scrum in the Google Docs application:

http://www.scrumology.net/2011/05/03/how-to-create-a-burndown-chart-in-google-docs/

The problem with it though is, it has only a place to update progress once per sprint but the burndown is supposed to be updated with daily progress, right? How can one modify this chart to be able to put daily progress on it?

I mean to be able to plot two lines (ideal and actual) with data such as (story points 255, velocity 24):

Actual Google Docs document (free to edit): https://docs.google.com/spreadsheet/ccc?key=0AuPWErnOiLTUdElJVzJZaE5EWEZ2S2xCelF6Z2lzaUE

Sprint Data

Sprint Chart

share|improve this question

2 Answers 2

The tutorial is really only showing you how to use a spreadsheet to draw a graph. As you say, in a Scrum project, you are probably more interested in the burndown within an iteration, on a daily basis. So simply take their approach and replace Iteration with Day. There's no magic about the name of the column in the spreadsheet.

share|improve this answer
    
The problem I see with it is how to plot Ideal line when you have daily updates. Basically, it comes to this - how to plot two lines based on two different time cycles there. –  Michał Minicki Jul 2 '12 at 6:54
    
You can just add more columns if you want more lines. But I don't really see what you're trying to do. You said you wanted to plot a daily burndown chart. That's all you need to run a sprint, eh? –  Dominic Cronin Jul 2 '12 at 12:39
    
I've added an example data (edited question) to make my question clearer. GDocs doesn't draw a line in this case for actual story points (because it has blanks) –  Michał Minicki Jul 3 '12 at 9:52

The tutorial you are referencing is very basic and meant to be customized :)

When I coach Scrum teams, I generally (not always) advise within the Sprint to:

  1. Burn down on task hours
  2. Burn up on story points

That way you can see how you are burning down on hours but balance that with actually completing stories.

share|improve this answer

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.