Estimation is the process of finding an estimate, or approximation, which is a value that is usable for some purpose even if input data may be incomplete, uncertain, or unstable.

learn more… | top users | synonyms

0
votes
1answer
124 views

How to handle a client that wants me to use code from Google under all circumstances? [duplicate]

I have a client that has been upset with the fact that it takes more time than he thinks to complete a feature / bug in a web application. He is more of a project manager that has hired me as a ...
1
vote
1answer
98 views

How long do you spend on analysis? Is this analysis paralysis? [duplicate]

I am not very good at estimating how long a piece of work will take to complete. I am guilty of putting my finger in the air and guessing. Usually things are later than expected, however sometimes ...
6
votes
3answers
5k views

How to estimate sprint velocity with varying team capacity?

We are a small team of 4 devs rather green in Scrum. Coming from all over the country, we often take odd days off or whole weeks off to go home. Therefore our team capacity changes dramatically from ...
27
votes
14answers
2k views

How to learn to make better estimates? [closed]

I suck at estimates. When someone asks me how long something will take, I don't even dare to make a guess since I will be completely off the mark. Usually I'm way too optimistic, and should probably ...
2
votes
4answers
228 views

Scrum task over estimation

In my current company we're using Scrum with 2 week iterations and a regular planning session. How planning normally works in our company is that we take a predefined , prioritized (by PO before the ...
0
votes
1answer
68 views

The place of UI design when estimating and elaborating user stories

Our company is trying to follow Agile methodologies when it comes to estimating and prioritizing any new development work. The reading I've done makes this concept appear great so we are trying to ...
47
votes
4answers
1k views

How can you estimate time for tasks which primarily consist of figuring out a problem?

While it is relatively possible for an experienced developer to estimate how long it will take to implement code when the pattern and problem the code is solving is well understood, how can you make a ...
6
votes
6answers
2k views

How many user stories per person should be completed per sprint? [closed]

Just ran across this figure, and wondering if there's another well know source than would help confirm these numbers: Based on data I analyzed on successfully finished sprints, I determined that ...
1
vote
1answer
140 views

Scrum: Baseline story for point estimation

To estimate PBIs you need to choose an average story and assign it a number of points (for example 5). Then you compare all other stories to that story and assign points accordingly. My question is, ...
3
votes
1answer
210 views

How do you work out timings for larger projects?

I work for a small company that hasn't done much work in bespoke development. It's something we're growing into. With all our projects, whether a bespoke development piece of work, or a simple ...
5
votes
4answers
2k views

In Scrum, what to do when story points and task hours don't roughly correlate?

Our development team is pretty new to the scrum process, so I would like to help refine our methods to make better use of it. In particular, I noticed that the correlation between story points and ...
70
votes
15answers
31k views

Why do we use story points instead of man days when estimating user stories?

In agile methodologies (e.g. SCRUM), the complexity/effort needed for user stories are measured in Story points. Story points are used to calculate how many user stories a team can take in an ...
2
votes
4answers
121 views

Estimation of your backlog

How far in advance should you estimate stories in your backlog? My concern is that estimates that are 6 months out will become out of date as you develop features in the current sprint. I thought ...
3
votes
1answer
163 views

Using function points as a metric for the velocity of a Scrum team?

I came across the idea of using function points as a metric for the velocity of a Scrum team. I saw it in a team and I found two articles mentioning a link between estimates and function points ...
3
votes
3answers
413 views

Effective way to estimate dead code removal?

I've been working in an application with about 100k LOCs and basically We have been reworking features to comply with a new architecture based on a new technology stack. This work is almost finished ...
4
votes
6answers
235 views

In scrum, how do you give an estimate for a backlog item that is primarily research?

A few sprints ago I was assigned a task that was primarily research. I had to figure out how to get our product to interoperate with a very complex black box that we did not develop. I couldn't ...
1
vote
5answers
1k views

Statistics on time estimates for web application

I have been asked to help estimate the time it would take to develop a web application. I will not be involved in the actual programming, but I am participating as an "experienced" programmer. The ...
1
vote
1answer
228 views

What is the significance of the output of Function Point analysis

I am a beginner in Software Engineering principles. This question have only academic significance. I read about Function Point analysis.We will be getting an integer value as output for Function ...
6
votes
4answers
321 views

Do you track progress during a agile sprint (iteration)

We have recently adopted (or are trying) to adopt managing our projects in an Agile manner. During our first sprint I asked our Scrum master (who also happens to be our primary resident Agile go-to ...
7
votes
9answers
2k views

How to answer “When will it be done?”

We all have it, problems that prove difficult to fix and working out a fix through obscure code and bizarre unexpected functionality. Slowly, logically working your way through trying to find ...
1
vote
1answer
91 views

Presenting agile estimates for Pivotal Tracker project

I've been developing for 6-7 years but never in a particularly agile way. With the latest project I'm trying to make our development process more professional, and more agile. We're using Pivotal ...
5
votes
1answer
193 views

Why is there a 20 and not 21 in some versions of Planning Poker?

In Planning Poker, cards usually contain numbers of the Fibonacci sequence, which is 0,1,1,2,3,5,8,13,21,34,55 etc. However, you can see on the Wikipedia page (and this has been confirmed to me by ...
2
votes
2answers
962 views

Story Point Estimation vs Ideal Days Estimation

In my project we assign 4 hours for 1 story point and estimate based on story point. So in this case one ideal day of work will be done in 2 elapsed days. From an agile standpoint are we doing story ...
0
votes
1answer
103 views

Story Point Estimation - Component Based

I have read that story point estimation is not intended to actually tie with number of hours , but is used to identify the relative capacity. I have a java application which has a adapter layer , a ...
0
votes
1answer
266 views

What is the best way to estimate when using Agile with Scrum? Hours or Story Points? [closed]

I was at a company that switched us over from Hours to Story Points for our estimations. I remember it being difficult to understand it, and we all chaffed against the idea. However, once we figured ...
1
vote
1answer
467 views

How do I count Internal Logical Files (ILF) and External Inputs (EI) for a dynamic form entry page? [closed]

Assuming I have an applicant information entry screen, the number and types of fields on which can be defined by the system administrator, how do I go about counting the number of Internal Logical ...
0
votes
2answers
172 views

estimation method at the “just finished definition phase”

We are basically using Waterfall life cycle methodology. Requirement Analysis: I get a use case created by some one else. Design (talking only about Low level design): I get some little feeling about ...
2
votes
3answers
486 views

Setting Deadlines in software development [duplicate]

I have been working on a system alone for about two years. I inherited the system from a contractor who spent about two years working on it before me (alone). The system is not particularly well ...
9
votes
5answers
1k views

The Relative Cost Efficiency of (Acceptance) Test Driven Development

I would like to know what the overall impact of resource planning on a software project is, where the requirements and design of the project are driven by automated acceptance tests and unit tests, in ...
4
votes
4answers
316 views

What do you do to estimates for agile stories where developers are pair programming?

If it was a 2-point story for one person, would you double it if people are pairing? Pairing isn't always necessarily done 100% of a dev task, so it seems that doubling the story points seems ...
5
votes
2answers
549 views

Is it okay to add time for “unexpected delays” to a time estimate?

I've landed my first contract (hooray, self employment!) and the company is asking for time estimates. Programmers are notoriously bad at time estimates, and I know I've been laughably wrong ...
0
votes
1answer
756 views

Are t-shirt estimates a good way to conduct initial estimates? [closed]

I've read articles with very conflicting arguments on t-shirt estimates. Neither article seemed all that credible so I thought I would bring this up here. Are t-shirt estimates a good idea? For ...
1
vote
2answers
510 views

How to factor in responsive design when providing an estimate for web applications?

In the past usually I have only had to estimate web applications based on browser support. But for more recent projects device and platform support are also very important as well (screen ...
48
votes
36answers
2k views

What can I do to get better at estimating how long projects are going to take? [duplicate]

I don't want to make life hard for management. I really don't. They're nice enough guys, but every time I am assigned a new project or task and get asked "how long do you think it will take to do ...
44
votes
4answers
1k views

How to explain to a non-technical person why the task will take much longer than they think?

Almost every developer has to answer questions from business side like: Why is going to take 2 days to add this simple contact form? When a developer estimates this task, they may divide it into ...
9
votes
10answers
823 views

User stories are too high level and conceptual, management expects developers to fill in the blanks

I am employed in a very brilliant company with a true intention of doing XP. Communication is good and management is open to constructive discussion but due to pressing time constraints, some certain ...
4
votes
4answers
207 views

Independency and estimation of user stories that rely on shared predecessor

Lest's say I have user stories about using product catalog in shop: As an administrator I can add/modify/delete catalog items (one or more user story, doesn't matter here) As a customer I can search ...
24
votes
13answers
1k views

Sales Manager: “Why is time-estimation so complex?” [duplicate]

A few days ago a sales manager asked me that question. But at this moment I didn't know a answer which he can understand. He isn't a programmer! At the moment I work on a product which is over 8 ...
4
votes
2answers
379 views

Efficient way to create a code estimation/technical specification in a fast-moving environment

To better understand my question, let me elaborate the background of the subject matter. I work in a financial institution where the business module (credit finance) is constantly changing. In the IT ...
5
votes
2answers
423 views

How do I survive in a Waterfall world? [duplicate]

I currently work in a company where the Waterfall model is deeply ingrained. We are pushing Agile principles but it's a long process. Meanwhile, I have to work in a Waterfall world with sequential ...
2
votes
2answers
644 views

What is the significance of 10 characters in this Uncle Bob post?

In this blog posting by Uncle Bob http://blog.8thlight.com/uncle-bob/2012/04/20/Why-Is-Estimating-So-Hard.html Author states a possible solution to the problem at hand. He writes "Try this. Break ...
1
vote
2answers
532 views

How to ensure a project 100% tested?

I want to know how exactly, we can ensure that a project is 100% tested ? In banking or financial applications not 1% also tolerable. So being a developer, how can you say your code is 100% tested? ...
2
votes
2answers
3k views

Closest Point of Approach (CPA) mathematical formula in ship radar

I was recently searching for the mathematical formula to find closest point of approach (CPA) between one ship and another ship. I need to apply the formula in my radar ship program and I can't find ...
0
votes
1answer
89 views

Tool helping with estimations [closed]

I am looking for a tool supporting me with estimations. What I would like to do is to specify a higher level task and break it into several smaller tasks. When a task is small enough, I could assign ...
1
vote
1answer
283 views

Metrics / Methodology for estimating resource utilization for software in planning stage

I'm looking for approaches to estimate the resource utilization of an (web-)application in a JEE environment. The overall target is to get a forecast for hardware/software requirements while the ...
4
votes
2answers
488 views

Daily Scrum Meeting (Burndown chart)

Here is an example: early in the morning of the second day of the Sprint (during the stand up) I go to the board and see that the story I worked the previous day (first day of Sprint) contains a big ...
19
votes
1answer
344 views

Has research been done on the effectiveness of Planning Poker as an estimation technique?

Although it is a commonly held opinion that planning poker improves the accuracy of project estimations (a small sample of which demonstrated on this question), has any defined research been done on ...
21
votes
10answers
2k views

How to add a new developer to the team

I run a small company composed of only 2 developers. We are building a very big application for one of our clients. Development on this project has gone on for 1.5 years. Now this client has secured ...
2
votes
2answers
221 views

If you have several SCRUM teams working on one backlog, how do you divide story point estimation between those teams?

I'm asking because approach in my company looks as follows: stories in the backlog are not estimated team that picks the story estimates it in story points during sprint planning part two
0
votes
1answer
352 views

What are the best practices and strategies for transferring an outsourced software development project in-house? [closed]

What are the best methods of knowledge transfer? What kinds of documentation should be expected? What activities should take place before and after handover, both by the external party and ...