Should a developer also act as a tester? [closed]

We're a scrum team of 3 developers, 1 designer, the scrum master, and the product owner. However, we don't have official tester in our team. A problem that is always with us, is that, testing the ...
11
votes
4answers
2k views

How to stop gold-plating and just be content to release working developments [closed]

The development team that I'm a member of has recently adapted to work according to Agile practices. This has personally highlighted the fact that I can't stop myself gold-plating code (and ...
20
votes
3answers
2k views

Scrum: how to handle backlog-items that are longer than one sprint

I'm starting with SCRUM and I have a problem understanding one thing. How does SCRUM handle backlog items that take longer than one sprint?
13
votes
12answers
12k views

With agile, what do when a user story doesn't get completed in an iteration? [duplicate]

Do you just move the story to a new iteration, or delay the next iteration? It gets a bit tricky when you use something like Jira when you have to copy or move around stories between iterations as it ...
53
votes
13answers
4k views

How can we reduce downtime at the end of an iteration?

Where I work we practice scrum-driven agile with 3-week iterations. Yes, it'd be nice if the iterations were shorter, but changing that isn't an option at the moment. At the end of the iteration, I ...
34
votes
10answers
5k views

Is unit testing or test-driven development worthwhile?

My team at work is moving to Scrum and other teams are starting to do test-driven development using unit tests and user acceptance tests. I like the UATs, but I'm not sold on unit testing for ...
10
votes
5answers
16k views

How to fit testing in Scrum sprints and how to write user stories in Scrum

I am the development team lead of a new project at my company. This is the first project where the company will use Scrum. We have a waterfall/iterative SDLC. The BAs write requirements docs, hands ...
5
votes
4answers
6k views

What is the purpose of the stand-up and its duration in agile methodologies? [closed]

I used to work in a waterfall methodology and now I am in a team that is following an agile methodology. It seems they are doing it wrong. For example, we have stand-ups that last 25+ minutes daily, ...
25
votes
4answers
7k views

How can a single developer make use of Agile Methods? [duplicate]

I am a freelancer and work as a single developer. In all cases, I am the person wearing different hats. I am the Scrum Master and I am the only person in the development. What I am not is the Product ...
26
votes
11answers
4k views

Scrum for a single programmer? [on hold]

I'm billed as the "Windows Expert" in my very small company, which consists of myself, a mechanical engineer working in a sales and training role, and the company's president, working in a design, ...
36
votes
13answers
6k views

Why and for what reasons developers may not like “daily scrum”? [closed]

There are advantages in holding daily scrum, like: Team get coordinated with each other Everyone knows what amount of task has been done Burndown chart gets more and more complete Task board is ...
9
votes
5answers
1k views

How to account for a bug fixing iteration?

We have implemented Scrum quite successfully for the past 5 months. Though, we are 3 weeks away from PROD without ever doing any end-to-end integration test. OUCH! I need help. Without tackling the ...
14
votes
7answers
2k views

Coding and testing in the same sprint

How is testing handled within the same sprint as coding, if all or most of the coding is not done until the end of the sprint? (I'm referring to the "soup-to-nuts" development and testing of a single ...
6
votes
4answers
417 views

Scrum roles mixed up

Here at the office our Scrum roles are a bit mixed up, so I would appreciate any advice on how to improve it. We are a small team of 4 developers (one of which is a de facto scrum master) and we also ...
88
votes
17answers
12k views

Does Scrum turn active developers into passive developers?

I'm a web developer working in a team of three developers and one designer. It's now about five months that we've implemented the agile scrum software development methodology. But I have a weird ...
48
votes
11answers
2k views

How can we make agile enjoyable for developers that like to personally, independently own large chunks from start to finish

We’re roughly midway through our transition from waterfall to agile using scrum; we’ve changed from large teams in technology/discipline silos to smaller cross-functional teams. As expected, the ...
19
votes
8answers
2k views

What have you seen go wrong when introducing SCRUM?

What was the single point of failure encountered when your company decided to replace the current processes with SCRUM? Can you give me some examples of things that have gone really wrong when a ...
17
votes
9answers
2k views

Are project managers useful in Scrum?

There are three roles defined in Scrum: Team, Product Owner and Scrum Master. There is no project manager, instead the project manager job is spread across the three roles. For instance: The Scrum ...
14
votes
16answers
5k views

Weeding out real agile from buzzword agile in an interview [closed]

I've been interviewing for co-ops (paid internships) lately and a large number of the companies I've been interviewing with have been saying they use Scrum or some other agile methodology (scrum being ...
12
votes
6answers
3k views

How to handle 'external' dependencies in scrum?

If you've planned a number of user stories for a sprint and one candidate story is dependent on some external provider delivering something to your team. For example an online service provider adding ...
10
votes
2answers
1k views

What to do with estimation of incomplete story?

I am part of a development team that is relatively new to Scrum, suppose that at the end of the sprint a few large stories are either in progress or were not accepted by the PO. Firstly, what ...
4
votes
1answer
247 views

Help, team members out of tasks want to start with future sprints topics

I have this problem, a team with 4 members working under scrum, with specific skills each one of them: Person A) DBA with reporting skills Person B) DBA with stored procedure skills and a very ...
4
votes
3answers
8k views

Confused about modifying the sprint backlog during a sprint

I've been reading a lot about scrum lately, and I've found what seem to me to be conflicting information about whether or not it's ok to change the sprint backlog during a sprint. The Wikipedia ...
19
votes
7answers
1k views

Do Scrum sprints mean to work at the fastest pace possible?

I recently interviewed with some companies that do Agile, Scrum to be more precise and there are some things that don't quite seem like Agile to me. I'll take one case that particularly interests me ...
6
votes
2answers
457 views

Scrum for Embedded system devices

In our company, we are going to deliver a new product which will be used for mass notification, so it is an embedded software project and we are going to use the SCRUM as a framework for the product. ...
4
votes
7answers
2k views

Do you estimate all user stories in iteration zero?

After our product backlog is created and prioritized, are we meant to briefly estimate all the stories in the product backlog? I assume they have to be in order to create a product burndown chart, ...
9
votes
5answers
1k views

What to do when a sprint is finished early?

What to do when a sprint is finished early? At the moment our Scrum team works off stories from the backlog, if the sprint is finished early. What happens with stories taken from the backlog? Will ...
9
votes
8answers
442 views

How can a team apply the Scrum methodology without a clear customer? [duplicate]

Our team is trying to understand and adapt Scrum and other agile practices, but we can not figure out how to deal with customer feedback when there is no customer. Every document about the subject ...
2
votes
2answers
589 views

QA - Developer communication [duplicate]

I am a developer and have worked at this company 4~5 years by now. We have been practicing scrum for about 2 years. I think, I have been worked well with QAs. I believe QAs/developers/technical ...
2
votes
2answers
2k views

How to adopt scrum agile methodology for a small .Net team [closed]

I am working on a small product based company developing .Net applications. There is a small team with 5-6 developers. I am a person responsible for planning everything. But my primary role is ...
0
votes
2answers
264 views

Scrum Sprint Optimization

Looking for a systematic method for estimating and comparing the success factors of sprint configurations based on: Team Size Sprint Duration Number of Stories
90
votes
15answers
56k views

Why do we use story points instead of man days when estimating user stories?

In agile methodologies (e.g. SCRUM), the complexity/effort needed for user stories are measured in Story points. Story points are used to calculate how many user stories a team can take in an ...
32
votes
17answers
6k views

Daily standups- yea or nay? [closed]

How valuable (or not) do you think daily stand-up meetings are? If you're not familiar with it, this refers to a daily meeting that is part of Scrum adherents (and some other agile methodologies). ...
24
votes
8answers
8k views

Story points for bug fixing tasks: Is it suitable for Scrum?

I'm just wondering if we should assign story points to bug fixing tasks or not. JIRA, our issues-tracking software, does not have story point field for Bug type issues (it's only for Storys and ...
24
votes
10answers
5k views

How does a Scrum team account for infrastructure tasks in the planning meeting?

How does a Scrum team account for dev/infrastructure tasks in the planning meeting? At first glance, they do not seem like user stories since they do not deliver end user value. However, attaching ...
17
votes
8answers
11k views

How do you deal with design in Scrum?

How do you deal with design in Scrum? Do you still have well written design documents for each scrum iteration? Do you just do design notes featuring UML diagrams? Or do you just have well commented ...
16
votes
4answers
2k views

How to adopt agile methodology for developing firmware/embedded-systems-software?

I've always wondered how to apply agile methods really are in large complex embedded system software (100+ engineers). Firmware development has some unique characteristics that make it difficult to ...
24
votes
6answers
4k views

How is Agile different from XP?

I read few articles on web to find out how Agile, XP, Scrum, pair programming are different from each other / related to each other and I derived the following line: Scrum and XP are almost same. XP ...
22
votes
9answers
2k views

Dominant team members in a Scrum team

What would you do in a situation where a team member tries to take responsibilities are not initially assigned to him but to the Scrum Master?
11
votes
5answers
915 views

Is it a good idea to appoint one of the scrum team member or scrum master as Product Owner?

Lately we had a project, in which client was busy touring. As usual scrum team was formed, management decided to appoint our analyst as Product owner since Client won’t be able to participate ...
27
votes
14answers
3k views

Does SCRUM usually involve massive overtime?

I would like to know if overtime is normal for sprints, or if it is an abuse of this methodology. I feel naive and spineless doing all-nighters if I don't have to. Question is SCRUM specific. ...
24
votes
7answers
10k views

Scrum - how to carry over a partially complete User Story to the next Sprint without skewing the backlog

We're using Scrum and occasionally find that we can't quite finish a User Story in the sprint in which it was planned. In true Scrum style, we ship the software anyway and consider including the User ...
18
votes
5answers
10k views

How do you keep track of a requirements document on an agile team?

I understand that User Stories dominate the agile world, but how are these artifacts stored, so that new developers who join the team can come up to speed with the requirements? What if the User ...
14
votes
6answers
4k views

Can scrum master allocate tasks?

We are following scrum in our project. I see most of the times the scrum master allocates the tasks for us. However, I read from many scrum books that scrum works the other way around (the 'pull' ...
19
votes
6answers
1k views

Is randomly refactoring code allowed in scrum

Background My team uses scrum I have currently no task assigned There are no more pending task in the backlog Today is Labor Day for my client. Not having many things to do today I wanted to start ...
19
votes
3answers
1k views

Are there any surveys regarding Scrum efficiency?

Years passed since Scrum had been widely adopted in software world. I’m wondering if there is any efficiency survey done by more or less independent people/institutes. Obviously scrums gurus who ...
14
votes
5answers
3k views

Keeping agile with zero-bug/defect policy

In our project we work in a zero-bug (a.k.a zero-defect) methodology. The basic idea is that bugs are always higher in priority than features. If you're working on a story and it has a bug it must be ...
6
votes
5answers
2k views

Who writes the technical 'user stories' in scrum

I know that a product owner should write a user story in scrum. A user story is describing a feature for the end user. But who describes what needs to be technically developed and how it needs to be ...
5
votes
5answers
2k views

Should you ever re-estimate user stories?

My current project is having a 'discussion' which is split down the middle- "this story is more complex than we originally thought, we should re-estimate" vs "you should never re-estimate as you only ...
11
votes
4answers
12k views

How long should a sprint planning meeting last?

In your experience, how long should a planning meeting (SCRUM) last? 8 hours? Or should it be shorter (succinct) and further discussions should be planned as part of the sprint (10 days sprint)?