4
votes
6answers
648 views

Should we create a story for vacation?

We have had a situation with a scrum sprint where a team member went on vacation for a few days at the beginning of the sprint. This led to us being behind the ideal trend on the burndown chart at the ...
1
vote
4answers
222 views

How does the product owner decide how successful a Sprint was? [closed]

Obviously if the product owner judges solely based on whether the committed stories were done, it wouldn't be good, because then the team will just commit to fewer stories next Sprint. On the other ...
0
votes
2answers
107 views

Product backlog- when do task hours get estimated?

I am wondering if when developing a product backlog do tasks have hours estimated for them. To confirm, i can talking about a product backlog here not a sprint backlog as I know it does have.
6
votes
4answers
270 views

Do you track progress during a agile sprint (iteration)

We have recently adopted (or are trying) to adopt managing our projects in an Agile manner. During our first sprint I asked our Scrum master (who also happens to be our primary resident Agile go-to ...
3
votes
4answers
419 views

Recommended sprint length when adopting Agile?

I'm new to a small development company (half a dozen programmers and should grow to possibly a dozen eventually). We also have a few external contractors working with us (just to add a bit of ...
39
votes
7answers
4k views

How to make sprint planning fun

Not only are our sprint planning meetings not fun, they're downright dreadful. The meetings are tedious, and boring, and take forever (a day, but it feels like a lot longer). The developers complain ...
7
votes
5answers
525 views

How do you demo software with No UI in the Sprint Review?

We are doing agile software development, basically following Scrum. We are trying to do sprint reviews but finding it difficult. Our software is doing a lot of data processing and the stories often ...
1
vote
4answers
237 views

Tracking progress via a burndown chart when sprints overlap

Our team has adopted some agile practices to help us develop and deliver our software to our client. We adopted practices as needed (as problems/challenges were identified) rather than jumping ...
7
votes
5answers
717 views

Scrum: Short VS long sprint

We were trying to figure out the optimal sprint length for our project. After working on a 3-weeks basis we thought that cutting the sprint to 2-weeks would provide better velocity. The advantages ...
2
votes
5answers
422 views

How to time the sprints in Scrum to allocate time for TDD?

We have sprints of 4 weeks duration. What I have been doing is 3 weeks dev time and 1 week of pure manual/automated testing, stabilization and shipment assurance testing. How to manage TDD within ...
5
votes
4answers
295 views

Can we pull future user stories in current sprint?

Suppose we have estimated 5 user stories to complete in a sprint and completed all of them with testing, buffer time and for expected bugs. Still we have 2-3 days left for one of the developer. Can ...
6
votes
3answers
276 views

Handling unexpected features during sprint

Our team is going to adopt scrum and agile technics. We've got a product, which we develop for multiple customers. This customers supplied us with necessary requirements, so everithing is fine to ...
3
votes
6answers
413 views

Finishing an iteration early

I'd like some input on this on those working with agile methodologies... A current project is finding that development on our planned user stories is finishing some time before the end of the ...
12
votes
9answers
684 views

How relaxed (or not) should a sprint be?

What should be the attitude towards getting stories done that are assigned to a sprint? Obviously you want to prioritize getting them done in the sprint, but to me the whole point of agile is to be ...
10
votes
4answers
328 views

Handling “related” work within a single agile work item

I'm on a project team of 4 devs, myself included. We've been having a long discussion on how to handle extra work that comes up in the course of a single work item. This extra work is usually things ...
6
votes
3answers
1k views

What happens between sprints?

I'm working on a project loosely following the scrum model. We're doing two week sprints. Something I'm not clear on (and don't have a book to consult) is exactly what is supposed to happen between ...
6
votes
3answers
535 views

Product Owner introduces ungroomed (unfamiliar, not estimated) User Story(s) into the Sprint Planning meeting

A problem that I am facing and would like some input into is; a Product Owner introduces ungroomed (unfamiliar, not estimated) User Story(s) into the Sprint Planning meeting. The issue that this has ...
3
votes
4answers
568 views

What is a clean Agile (Scrum) Sprint Presentation?

Suppose someone of your development team is presenting a sprint to the customer but he is having web connection problems such that a complete story cannot be presented. For the sake of the cleanness ...
7
votes
5answers
3k views

Calculating last Sprint's Focus Factor

We have finished our Sprint in half the expected time and now we want to compute our focus factor to use in the next Sprint. Though, by doing the math by the book, we get an awful number. How are we ...
4
votes
3answers
638 views

Scrum on very short projects?

I'm using Scrum and really liking it. However, my shop finds itself in projects where the duration of the development effort is two or four weeks. We've already modified the sprint length to two ...
2
votes
3answers
168 views

Defer items during sprint or at the end of sprint

When tasks take longer than expected, why is it better to defer items during a sprint than to just defer everything you didn't finish on the last day of the sprint?
2
votes
1answer
360 views

who should move the sprint status to complete in agile scrum model

we ask the developers themselves to close the sprint once they completed the sprint. Just want to confirm, if it has to be closed by TL after he reviewed the tasks completion.
6
votes
4answers
472 views

Sprint Meetings - What to talk about

In work we have just started using the Scrum methodology, it is working well but I have a question on the daily sprint meetings. We set aside 15 minutes for the meeting (between the three devs and ...